Repairs of key backup power line begin at occupied Zaporizhzhia NPP

Repairs of key backup power line begin at occupied Zaporizhzhia NPP

Ukrinform
With the mediation of the International Atomic Energy Agency, repair work has begun on the 330 kV backup power transmission line Ferosplavna-1, which connects the Zaporizhzhia Nuclear Power Plant to Ukraine's power grid. 

The IAEA reported this on the social media platform X, according to Ukrinform.

"Crucial repair works on the essential backup Ferosplavna-1 330 kV power line connecting Ukraine's ZNPP to the grid have begun under another IAEA-brokered ceasefire," the statement said.

The repairs are being carried out by a Ukrainian technical team, while IAEA specialists are present on site and are monitoring the progress of the work.

Read also: Shmyhal supports completion of new nuclear power plant units

As Ukrinform reported, according to the Ministry of Energy, since the start of the full-scale invasion Ukrainian power engineers have restored the Zaporizhzhia NPP's power supply lines 42 times.

Photo: IAEA

While citing and using any materials on the Internet, links to the website ukrinform.net not lower than the first paragraph are mandatory. In addition, citing the translated materials of foreign media outlets is possible only if there is a link to the website ukrinform.net and the website of a foreign media outlet. Materials marked as "Advertisement" or with a disclaimer reading "The material has been posted in accordance with Part 3 of Article 9 of the Law of Ukraine "On Advertising" No. 270/96-VR of July 3, 1996 and the Law of Ukraine "On the Media" No. 2849-Х of March 31, 2023 and on the basis of an agreement/invoice.

Online media entity; Media identifier - R40-01421.

© 2015-2026 Ukrinform. All rights reserved.

Extended searchHide extended search
By period:
-