Another TPP power unit put into operation following repairs - Energy Ministry

Another TPP power unit put into operation following repairs - Energy Ministry

Ukrinform
Two days ahead of schedule, the repair of another power unit of a Ukrainian thermal power plant was completed, which allowed adding 160 MW of power to the energy grid.

This was reported by the press service of the Energy Ministry, Ukrinform reports.

"Yesterday, at one of the TPPs, a power unit came out of repair two days ahead of schedule, which added an additional 160 MW of power to the energy grid. The electricity generated by Ukrainian power plants is sufficient to meet consumers’ needs," the report reads.

Read also: Azerbaijan to provide more equipment to restore Ukraine's power grid this year

It is also noted that work is underway to restore gas supply to consumers who were disconnected due to the strike that targeted the gas transmission system in Kharkiv region overnight Thursday, October 12. Currently, 6,800 households have been reconnected to the grid, while 6,700 remain without gas supply.

While citing and using any materials on the Internet, links to the website ukrinform.net not lower than the first paragraph are mandatory. In addition, citing the translated materials of foreign media outlets is possible only if there is a link to the website ukrinform.net and the website of a foreign media outlet. Materials marked as "Advertisement" or with a disclaimer reading "The material has been posted in accordance with Part 3 of Article 9 of the Law of Ukraine "On Advertising" No. 270/96-VR of July 3, 1996 and the Law of Ukraine "On the Media" No. 2849-Х of March 31, 2023 and on the basis of an agreement/invoice.