Water supply stops in Vinnytsia due to power outage, station restart underway

Water supply stops in Vinnytsia due to power outage, station restart underway

Ukrinform
In Vinnytsia, the main water supply station stopped working due to a power outage, and it will take up to 6 hours to fully restore the water supply.

This was reported by Vinnytsiaoblvokanal on Facebook, according to Ukrinform.

Due to a complete lack of electricity, the main water supply station in Vinnytsia stopped working. It is noted that the entire city is currently without water.

“As of now, the power supply has been restored. According to information from Vinnytsiaoblvokanal, power has been restored and the main water supply station has begun to restart,” according to a post by the Vinnytsia City Council on Telegram.

It is noted that it will take at least 5-6 hours to fully restore water supply in all microdistricts of the city.

As reported by Ukrinform, train service and escalator operation in the Kyiv metro were temporarily suspended due to a power outage from external power supply centers.

Photo: unsplash

While citing and using any materials on the Internet, links to the website ukrinform.net not lower than the first paragraph are mandatory. In addition, citing the translated materials of foreign media outlets is possible only if there is a link to the website ukrinform.net and the website of a foreign media outlet. Materials marked as "Advertisement" or with a disclaimer reading "The material has been posted in accordance with Part 3 of Article 9 of the Law of Ukraine "On Advertising" No. 270/96-VR of July 3, 1996 and the Law of Ukraine "On the Media" No. 2849-Х of March 31, 2023 and on the basis of an agreement/invoice.

Online media entity; Media identifier - R40-01421.

© 2015-2026 Ukrinform. All rights reserved.

Extended searchHide extended search
By period:
-